The Mesa A Dig Off Pads project for RTIO Sustaining Capital involved the construction of two new dig off pads. The scope of work included vegetation clearance, topsoil stripping, embankment construction, pavement supply, installation of new signage, and the setup of two solar work lights. Additionally, the project included realigning the current rail access track around the new dig off pads.
Highlights of the project included completing all works without any incidents, demonstrating a strong commitment to safety. RTIO recognised the project team for their proactive safety participation and input, with operator Kimi receiving a safety award. Importantly, the project was executed without any disturbance to restricted access areas, ensuring compliance with environmental and operational requirements.
Projects
Client
RTIO Sustaining Capital
Location
Mesa A
Duration
8 weeks
Cost
$1.1 million